Skippack Township residents are advised that roadway milling and paving operations will begin next week as part of the Township's ongoing road maintenance and improvement program.
Preparatory work, including pre-construction core sampling, will be completed prior to the start of construction activities. "No Parking" signs will be posted in affected areas beginning this week to notify residents of temporary parking restrictions and to help ensure the work can be completed safely and efficiently.
Project Schedule
Monday, June 8 – Milling
Thursday, June 11 – Paving
- Tranquility Street
- Andrew Court
Tuesday, June 9 – Milling
Friday, June 12 – Paving
- Victoria Drive
- Erin Drive
- Christina Drive
Wednesday, June 10 – Milling
Monday, June 15 – Paving
- Ironbridge Drive
- Mockingbird Lane
- Wingate Drive
Thursday, June 11 – Milling
Tuesday, June 16 – Paving
- Skipview Lane
Important Information for Residents
Residents living on affected streets should be prepared for temporary traffic delays, construction equipment, and parking restrictions during milling and paving operations. Please observe all posted signage and avoid parking on roadways during scheduled work hours.
The Township appreciates residents' patience and cooperation as these improvements are completed. Please note that the schedule is weather dependent and may be adjusted if necessary.
For updates regarding this project, please continue to monitor the Skippack Township website and our Facebook page.