Allan Myers has informed us that due to last week’s and this morning’s rain, the start of paving is now scheduled for this Friday morning. Also, as a result of the delay, they will also be working this Saturday morning to make up some of the lost time. Below is an updated schedule of work. Again, the exact timing is weather dependent, however this is the order of the work. Allan Myers delivered notices to every house in the neighborhood this past Friday and no parking signs will be posted at least 24 hours in advance of work starting in each area of the neighborhood. Please contact Township Manager Chris Heleniak at 610-454-0909 or cheleniak@skippacktownship.org with any questions.